You can determine which fixed assignments to load from the project settings .qsf, and optionally load the latest placement from Logic Generation. The enabled assignments become the starting point for the tile plan. Follow these steps to update the plan with existing assignments:
  1. On the Flow control, click View Assignments.
    Figure 28. Plan Assignment Options
  2. On the Assignments tab, select the assignment types to load for the current planning session, as Assignments Tab Controls describes.
  3. On the Assignments tab, enable or disable assignments to resolve any conflicts or experiment with alternative placements. Filter the list of assignments by assignment name or status.
    Figure 29. Enable or Disable Existing Assignments for Current Planning Session
  4. When assignment selections are complete, or if you have no existing assignments, click Update Plan on the Flow control to apply the enabled project assignments to your current tile interface plan.
  5. Place IP components and building blocks on the Plan tab, as Step 4: Create a Tile Plan describes.